Bridge delay claim denied

Tutor Perini sought §22,941,971.68 for a two-year delay caused by a court injunction. In 2013, Tutor Perini Corporation entered into a $102 million contract with the Department of Transportation to replace the City Island Road bridge that spans Eastchester Bay between the Bronx and City Island. A state court injunction delayed the construction of the bridge for two years and forced the redesigning of the bridge.


City Planning Approves New City Island Bridge

New causeway design for City Island Bridge applauded by community and local elected officials. On May 21, 2014, the City Planning Commission unanimously approved an application by the New York City Department of Transportation and Department of Parks and Recreation for a city map amendment to facilitate the construction of a new City Island Bridge in the Bronx. City Island Bridge, which connects City Island to Rodman’s Neck, was built in 1901 and was determined … <Read More>