DDC Announces Six Firms to Compete for Borough-Based Jails Projects

Design-build teams have already been selected to handle the demolition of structures on the current sites. On December 29, 2021, the Department of Design and Construction announced that six teams have been approved to develop detailed proposals for the design and construction of four smaller borough-based jails in Manhattan, Queens, Brooklyn, and the Bronx. The borough-based jails project aims to replace the facilities on Rikers Island permanently with smaller jails that will allow for populations <Read More>


First Design-Build Teams Selected, Construction to Soon Begin on Borough-Based Jails Project

These teams will prepare the site for construction and enable court operations to continue for the duration of construction. On November 30, 2021, the Department of Design and Construction announced that four separate teams had been selected to receive design-build contracts to prep the sites of the new Borough-Based Jails. The Borough Based Jails project will build smaller jails in Manhattan, the Bronx, Queens and Brooklyn to allow for the eventual closure of Rikers Island <Read More>


DDC Announces Mentoring Program for Qualified M/WBE Construction Firms and Small Businesses

The program provides training, networking, and bidding opportunities. On November 10, 2021, the Department of Design and Construction (DDC) announced the launch of a DDC Mentoring Program designed to support and increase business opportunities for Minority- and Women- Owned Business Enterprises (M/WBEs). As the principal construction management agency for New York City, the DDC is responsible for many City contracting opportunities and projects with M/WBE firms. The program was modelled after successful mentoring programs at <Read More>


Mayor de Blasio Appoints Tom Foley as Acting DDC Commissioner

Foley is a 23-year veteran of the agency. On October 28, 2021, Mayor Bill de Blasio appointed Tom Foley as the Acting Commissioner for the Department of Design and Construction (DDC). The appointment comes as Commissioner Jamie Torres-Springer, who had been appointed in March, prepares to depart on November 12th to become the President of Construction and Development at the MTA. 


DDC Provides Progress on Completion of Part of East Side Coastal Resiliency Floodwall

The phased construction of the project ensures there will still be parkspace and waterfront accessible to residents during the duration of the project. On October 6, 2021, the NYC Department of Design and Construction (DDC) announced the completion of 500 feet of floodwall as part of the East Side Coastal Resiliency Project (ESCR). The new floodwall has been installed in the area north of Stuyvesant Cove Park along the East River. The ESCR project is … <Read More>


City Furthers Progress on Downtown Far Rockaway Reconstruction

The project will enhance economic opportunity for Queens residents and prevent future flooding. On August 2, 2021, the New York City Economic Development Corporation, and the Departments of Environmental Protection, Transportation, and Design and Construction announced the completion of Phase 1 of a $139 million project to revitalize Downtown Far Rockaway’s infrastructure. Phase 1 was completed ahead of schedule, 21 months after the project was first announced.